السؤال — عربي
: يُستخدم مقياس "التكلفة المدرجة في الموازنة للعمل المنجز" (Budgeted cost of work performed) بشكل أفضل لقياس أي نشاط من أنشطة إدارة المشاريع؟
Question — English
The budgeted cost of work performed is a metric best used to measure which project management activity?
الخيارات — عربي
Options — English
💡 The budgeted cost of work performed (BCWP) is a key metric in
earned value management (EVM) that helps measure project
performance by comparing the value of work actually completed
to the planned budget. This metric is essential for cost control
because it allows project managers to: Track project spending
against planned costs / Identify cost overruns or savings. / Take
corrective actions if the project is deviating from the budget.