أي مما يلي يُعد منهجية تخطيط مشاريع تتضمن سلسلة معقدة من المحاكاة لتوفير معلومات حول مخاطر الجدول الزمني؟
Question — English
Which of the following is a project planning methodology that involves a complex series of required simulations to provide information about schedule risk?
الخيارات — عربي
Options — English
💡 A. Monte Carlo Analysis → Correct Answer. Monte Carlo
analysis is a project planning methodology used to
assess risk and uncertainty in project schedules and
outcomes. It involves running simulations using random
variables to estimate the probability of different project
completion times, helping to identify schedule risks.
B. Project Management Information System (PMIS) →
This is a system used for managing project information,
including planning, monitoring, and controlling. While it
helps in tracking and managing data, it doesn't
specifically involve simulations for schedule risk like
Monte Carlo analysis.
C. Earned Value Management (EVM) → EVM is a
method used to assess a project's performance by
comparing the planned progress against the actual
performance. It focuses on cost and schedule
performance but does not specifically involve
simulations like Monte Carlo analysis.
D. Integrated Project Plan → This is a comprehensive
plan that integrates all aspects of project management,
including scope, schedule, and cost. However, it does
not involve simulations for schedule risk assessment like
Monte Carlo analysis.